学者谷

位置:首页 > 校园范文 > 其他

根据监理/业主指令写变更的Proposal

其他1.54W

一般根据合同规定,业主或监理有权根据自己的意愿对合同进行变更,如:

根据监理/业主指令写变更的Proposal

Right to Vary

Variations may be initiated by, the Employers Representative at any time during the Contract Period, either by instruction or by a request for the Contractor to submit a proposal. If the Employers Representative requests the Contractor to submit a proposal and subsequently elects not to proceed with the changes, the Contractor shall be reimbursed for the Cost incurred, including design services.

The Contractor shall not make any alteration and/or modification of the Works, unless and until the Employers Representative instructs or approves a Variation. If the Construction Documents or Works are not in accordance with the Contract, the rectification shall not constitute a Variation.

注:Employer`s Representative是指监理,对于变更的权利,大家一定要仔细看一下监理的权力范围(监理职责和权力的条款),大部分情况下,合同里面会规定监理无权变更合同,所以对于监理的变更令,一定要有业主的书面确认,否则无效,建议不予理会。


这个时候业主/监理如果指示变更,那你作为承包商就要对他们指示的变更做一个建议书(Proposal),其实这个也很简单,就跟你投标时候一样的,他有什麽需求,你根据他的需求写个方案,如果他这个需求涉及到技术方面的,那么这个方案就包括两方面,第一是技术建议书(Technical Proposal),第二部分是财务建议书(Financial Proposal)。


对于你们不愿意满足的需求,那么技术建议书难度做大一点,财务建议书金额做高高的,那么业主/监理也就望而却步了。


对于你们乐意去做的变更,而且有利可图的,那么技术建议书做的中肯点,财务建议书可以做高点,但是财务建议书要理性。


在提交之前,尤其是业主/监理口头指示的',我建议先非正式地给业主/监理看看电子版,他们如果同意就发,不同意可以修改。如果他们望而却步了,而且是口头指示的,那就不发了,直接当没有这回事儿发生,尽量做到越少人知道越好。


至于格式一般是写一个Cover Letter,说后面附上的是建议书,然后建议书单独分成两部分,一个技术建议书,一个财务建议书。说over Letter,执行的性质令没头没岛建议书金额做高一点


忌讳:往往监理/业主的指示都很简单,不具备可执行性,所以不要业主/监理一指令(无论是口头还是书面的),就根据他们的指令没头没脑地开始干活儿,一定要搞清楚他们真正的需求(比如他们是想你们多干活儿且多给钱还是多干活儿也不给钱,他们到底是要做到什么程度),所以要提交建议书,尤其是财务建议书,他们同意才开始实施,如果他们不同意,就当他们什么也没有指示,依然按合同干就完了。